Broad Lane Update

The good news is that contractors for Severn Trent say the work on Broad Lane is ahead of schedule.

 The bad news is that the next stage will be very disruptive for residents going to and from Wood End Station and the Birches Medical Centre.

Phase Three from Vicarage Hill to The Common will be done in two stages.

Initially, there will be no access to Broad Lane or Poolhead Lane from Vicarage Hill.  Residents will have to approach the station and the Surgery from Tom Hill.

When the section to the Surgery is complete Poolhead Lane will re-open to traffic and access to the Surgery will be via Vicarage Hill only until the work is completed.

Planned work by contractors on behalf of BT Openreach which was due to start on 15 June will now begin at a later date. 

The area from the Bell on The Green down Doctor’s Hill to and including Knowlebury Cross will be closed to vehicular traffic.

(Source: Tom Ross)